Skip to content
Article · · 11 min read · By Ruth

Shop Drawing Approval Process: Panel GA Drawing Submittals in Kenya

Understand the shop drawing approval process for custom electrical panels, from GA drawing preparation and technical submittal to consultant comments, revisions and final approval

Shop Drawing Approval Process: Panel GA Drawing Submittals in Kenya

The shop drawing approval process ensures that a proposed electrical panel matches the approved electrical design before manufacturing begins. For LV panels, the process normally moves from technical submittal and GA drawing preparation through consultant review, comments, revisions and final approval.

For custom switchboards, manufacturing should not begin simply because a purchase order has been issued.

The manufacturer, contractor and consultant need to establish that the proposed panel arrangement matches the project's electrical requirements.

This is where panel GA drawing submittal becomes important.

A well-prepared submittal can reduce design clarification, manufacturing changes and programme delays.

Paneltech Systems Ltd provides LV panels and electrical engineering solutions for commercial, industrial and infrastructure applications.


What Is the Shop Drawing Approval Process?

The shop drawing approval process is the formal review of detailed manufacturer drawings before equipment is fabricated or installed. The consultant checks the proposed equipment against the approved design, specifications, schedules and project requirements.

The typical sequence is:

Design → Procurement → Technical Submittal → GA Drawings → Consultant Review → Comments → Revision → Approval → Manufacturing → Testing → Delivery

The exact process varies by project contract.

However, the fundamental objective remains the same:

Confirm the equipment before committing to manufacture.

For custom LV panels, this review is particularly important because dimensions, component arrangement, cable entry and internal construction may differ between manufacturers.


What Is a Panel GA Drawing?

A panel GA drawing, or General Arrangement drawing, shows the physical arrangement and major dimensions of the electrical panel. It allows the consultant and contractor to verify enclosure dimensions, doors, equipment locations, cable entries and installation requirements.

A typical GA drawing may show:

  • Panel overall width
  • Panel overall height
  • Panel depth
  • Number of sections
  • Doors
  • Mounting arrangements
  • Breaker locations
  • Metering
  • Control devices
  • Cable entry
  • Gland plates
  • Busbar compartments
  • Foundation details
  • Lifting provisions
  • Panel weight

The GA drawing should correspond with the electrical design.

For example, if the approved single-line diagram shows an ACB incomer and eight MCCB feeders, the GA drawing should provide a physically realistic arrangement for those components.


What Documents Are Included in a Panel Submittal?

A complete electrical panel submittal should contain more than the GA drawing. It should provide sufficient technical information for the consultant to verify ratings, components, construction, protection and compliance before approval.

A typical submittal package can include:

  1. General Arrangement drawing
  2. Single-line diagram
  3. Schematic diagrams
  4. Component schedule
  5. Technical datasheets
  6. Protection-device information
  7. Metering details
  8. Busbar details
  9. Enclosure information
  10. Cable-entry details
  11. Terminal schedules
  12. Compliance documentation
  13. Type/design verification information where applicable
  14. Proposed testing procedure
  15. Deviations schedule

The required documents should follow the project specification.


Step 1: Review the Approved Electrical Design

The manufacturer should review the approved electrical drawings and schedules before preparing shop drawings. This prevents the GA drawing from being developed from incomplete or outdated information.

The review should include:

  • Single-line diagrams
  • Panel schedules
  • Load schedules
  • Cable schedules
  • Equipment schedules
  • Electrical specifications
  • Architectural drawings
  • Mechanical requirements
  • Room layouts
  • Project standards

The manufacturer should identify discrepancies before submitting drawings.

For example:

If the panel schedule specifies a 630 A incomer, but the single-line diagram shows 800 A, clarification should be obtained before the GA drawing is finalised.


Step 2: Prepare the Technical Submittal

The technical submittal provides the consultant with the manufacturer's proposed equipment and components for review. It should demonstrate that the proposed panel can meet the project's electrical and performance requirements.

The technical submittal can include:

  • Manufacturer information
  • Proposed breaker brands
  • Metering equipment
  • Contactors
  • Relays
  • VFDs
  • APFC controllers
  • SPDs
  • Enclosure materials
  • Busbar systems
  • Protection devices

Where the project specification identifies approved manufacturers, the submission should demonstrate compliance with those requirements.

Where alternatives are proposed, they should be clearly identified.


Step 3: Prepare the Panel GA Drawing

The GA drawing converts the electrical design into a physical panel arrangement. It should show enough information for the consultant and contractor to confirm that the proposed enclosure will fit the space and accommodate all required equipment.

The drawing should normally identify:

Overall Dimensions

  • Height
  • Width
  • Depth

Panel Sections

  • Incomer section
  • Busbar section
  • Outgoing feeder section
  • Control section
  • Metering section

Access

  • Front access
  • Rear access where required
  • Door swing
  • Removable covers

Cable Entry

  • Top
  • Bottom
  • Side

Installation

  • Floor-mounted
  • Wall-mounted
  • Plinth-mounted

These details can have significant consequences if discovered after manufacturing.


Step 4: Submit the Drawings Through the Correct Channel

The shop drawing approval process should follow the project's document-control procedure. Drawings should be submitted through the designated contractor, consultant or document-control system rather than relying on informal approvals.

A proper submission should identify:

  • Project name
  • Drawing title
  • Drawing number
  • Revision
  • Submission date
  • Manufacturer
  • Contractor
  • Consultant
  • Status

The drawing should also have a clear revision history.

This creates an auditable record of what was submitted and what was approved.


Step 5: Consultant Review

During consultant review, the panel drawing is checked against the approved design, specifications and project conditions. The consultant may approve the drawing, approve it with comments, request revisions or reject it.

Typical review areas include:

Electrical

  • Voltage
  • Current
  • Fault rating
  • Breaker selection
  • Protection
  • Metering
  • Busbar arrangement

Mechanical

  • Dimensions
  • Weight
  • Access
  • Cable entry
  • Mounting
  • Ventilation

Functional

  • Controls
  • Interlocks
  • Alarms
  • Automation
  • Communication

Compliance

  • Applicable standards
  • Project specification
  • Approved component requirements
  • Testing requirements

Common Shop Drawing Approval Statuses

Project teams may use different approval codes, but most systems distinguish between approved drawings, drawings requiring comments or revisions, and drawings that cannot proceed. The exact meaning of each status should be defined in the project's document-control procedure.

Common descriptions include:

Status Meaning
Approved Proceed according to approved drawing
Approved with Comments Proceed subject to stated comments
Revise and Resubmit Changes required before approval
Not Approved Major issues must be resolved
For Information Submitted for record/information
Superseded Replaced by a newer revision

Manufacturers should never assume that a drawing marked “Revise and Resubmit” is permission to manufacture.


What Consultants Check on a Panel GA Drawing

Consultants should check both technical and physical aspects of the GA drawing before approving it. The drawing should be consistent with the single-line diagram, panel schedule and project installation requirements.

A practical review checklist includes:

Panel Identification

  • Panel tag
  • Panel description
  • Drawing number
  • Revision

Dimensions

  • Width
  • Height
  • Depth
  • Section dimensions

Equipment

  • ACBs
  • MCCBs
  • MCBs
  • Contactors
  • Relays
  • Meters
  • Controllers

Construction

  • Enclosure material
  • IP rating
  • Mounting
  • Access
  • Cable entry

Electrical

  • Busbar rating
  • Incomer rating
  • Feeder arrangement
  • Neutral
  • Earth bar

Installation

  • Room location
  • Access clearance
  • Cable routes
  • Plinth requirements

Why the Single-Line Diagram Must Match the GA Drawing

The single-line diagram describes the electrical function while the GA drawing describes the physical implementation. Both drawings must represent the same equipment and feeder arrangement.

Consider a simplified example:

The SLD shows:

800 A ACB → 400 A MCCB → 250 A MCCB → 160 A MCCB

The GA drawing should provide appropriate physical space and identify these devices correctly.

A mismatch can cause:

  • Procurement errors
  • Incorrect breaker selection
  • Manufacturing changes
  • Delayed approval
  • Installation problems

The SLD should therefore be treated as a key reference document during shop drawing preparation.


Panel GA Drawing and Cable Entry Coordination

Cable-entry arrangements should be confirmed before the panel is manufactured because changing entry locations after fabrication can require physical modification. The GA drawing should therefore show the intended cable-entry direction and gland-plate arrangement.

The team should confirm:

  • Incoming cable size
  • Number of cables
  • Cable entry direction
  • Gland type
  • Armouring
  • Bending radius
  • Termination space
  • Cable trench location

For large cables, inadequate termination space can become a serious installation problem.


Panel Dimensions and Electrical Room Coordination

Panel dimensions must be coordinated with the electrical room before approval. A panel that satisfies electrical requirements but cannot be transported, installed or maintained properly can still cause a project delay.

Check:

  • Door openings
  • Access routes
  • Stairways
  • Lifts
  • Ceiling height
  • Panel working clearance
  • Cable trench
  • Adjacent equipment
  • Generator or transformer connections

The contractor should confirm the proposed dimensions against actual site conditions.


Internal Panel Arrangement

The internal arrangement should provide practical access to breakers, terminals, wiring and other components while maintaining the required separation and electrical clearances.

The consultant should consider:

  • Busbar position
  • Breaker arrangement
  • Cable termination areas
  • Control components
  • Metering
  • Terminal blocks
  • Spare space
  • Maintenance access

A compact panel is not necessarily a better panel if maintenance becomes difficult.


Technical Submittal Review for Breakers

Breaker submittals should be reviewed for voltage, current, breaking capacity, trip characteristics and required protection functions. The selected breaker should match the project's fault and load calculations.

For an MCCB or ACB, the review may include:

  • Rated current
  • Rated voltage
  • Breaking capacity
  • Short-time withstand
  • Long-time protection
  • Short-time protection
  • Instantaneous protection
  • Earth-fault protection
  • Adjustable settings
  • Auxiliary contacts
  • Undervoltage release
  • Shunt trip
  • Communication

The requirements will depend on the project.


Shop Drawing Approval for APFC Panels

APFC panel drawings should show the capacitor stages, switching equipment, controller, protection and connections to the electrical system. The design should also account for the characteristics of nonlinear loads where applicable.

The consultant may check:

  • APFC rating
  • Capacitor stages
  • Controller
  • Contactors or switching devices
  • Capacitor protection
  • Harmonic conditions
  • Cooling
  • Metering
  • Incoming protection

Paneltech Systems provides APFC panel solutions for suitable applications.


Shop Drawing Approval for VFD Panels

VFD panel drawings should show the drive arrangement, incoming protection, motor connections, control wiring and required bypass or isolation equipment. The design should also provide appropriate ventilation and heat-management provisions.

The review should consider:

  • VFD rating
  • Motor rating
  • Input breaker
  • Input isolator
  • Output connections
  • Bypass arrangement
  • Control interface
  • Emergency stop
  • Communication
  • Ventilation

Paneltech Systems provides VFD drive solutions for applicable motor-control applications.


Shop Drawing Approval for MCC Panels

MCC shop drawings should coordinate every motor feeder with the motor schedule and control philosophy. The consultant should verify starter types, protection, VFDs, controls and physical arrangement before approval.

The MCC review should include:

  • Motor ratings
  • Starter type
  • VFDs
  • Overload protection
  • Short-circuit protection
  • Local/remote control
  • PLC interface
  • Indication
  • Emergency stops
  • Spare feeders

The panel should correspond with the approved motor-control philosophy.


Revision and Resubmission

When a consultant identifies issues, the manufacturer should revise the drawing and clearly identify the changes. The revised drawing should receive a new revision number so that obsolete versions are not accidentally used.

A good revision process includes:

  1. Record consultant comments
  2. Review each comment
  3. Make required changes
  4. Update drawing revision
  5. Update revision description
  6. Reissue drawing
  7. Submit response to comments
  8. Obtain approval

The manufacturer should retain previous revisions for document-control purposes.


Common Reasons Panel Drawings Are Rejected

Panel drawings are commonly returned because of inconsistencies, missing information, incorrect dimensions or failure to follow the project specification. Most of these problems can be prevented through an internal pre-submission review.

Common issues include:

1. Incorrect Panel Dimensions

The proposed enclosure does not fit the allocated space.

2. Missing Cable Entry

The drawing does not show how cables will enter the panel.

3. SLD and GA Mismatch

The physical arrangement does not match the approved electrical design.

4. Wrong Breaker Ratings

The selected protection does not correspond to the approved schedule.

5. Missing Metering

Required meters or CTs are omitted.

6. Incomplete Earthing

Earth-bar arrangements are unclear.

7. Unapproved Components

Proposed equipment does not meet the approved manufacturer requirements.

8. Missing Technical Data

Datasheets or compliance documentation are absent.

9. No Revision History

The drawing does not clearly show what has changed.

10. Poor Drawing Quality

Important dimensions, labels or component references cannot be read.


How to Avoid Shop Drawing Approval Delays

The best way to shorten the shop drawing approval process is to submit complete, coordinated drawings that have already undergone an internal technical review. Early clarification of dimensions, components and project requirements prevents avoidable resubmissions.

Before submission:

  • Check the latest SLD
  • Check the latest panel schedule
  • Confirm load ratings
  • Confirm breaker ratings
  • Confirm dimensions
  • Confirm cable entry
  • Check room layout
  • Confirm approved components
  • Review applicable standards
  • Check drawing references
  • Update revision numbers
  • Include all required datasheets

A manufacturer's internal review can catch many problems before the consultant sees them.


Who Is Responsible for Shop Drawing Approval?

Responsibility depends on the project contract, but the manufacturer normally prepares the technical drawings while the contractor coordinates the submission and the consultant reviews them against the design requirements. Approval does not remove each party's contractual responsibilities.

A typical responsibility structure is:

Party Typical Responsibility
Consultant Design criteria and technical review
Contractor Coordination and formal submission
Manufacturer Detailed shop drawings and technical data
Client Review/approval where contractually required
Site Team Installation coordination
Commissioning Team Testing and operational verification

The actual contractual responsibilities should always take precedence.


Shop Drawing Approval Timeline

The time required for approval depends on the project's document-control procedure, drawing complexity and number of review cycles. Early submission is important because panel manufacturing should allow sufficient time for review, revision, testing and delivery.

A simplified workflow is:

Stage Activity
1 Review approved design
2 Prepare technical submittal
3 Prepare GA drawings
4 Internal manufacturer review
5 Contractor submission
6 Consultant review
7 Comments issued
8 Manufacturer revision
9 Resubmission
10 Final approval
11 Manufacturing
12 Factory testing
13 Delivery
14 Installation
15 Site testing and commissioning

The earlier the technical submission starts, the more opportunity the project team has to resolve design issues before procurement becomes critical.


Shop Drawing Approval System Specifications

A complete panel submittal should provide both physical and electrical information so that the reviewer can assess the proposed assembly before manufacturing. The exact requirements should follow the project specification and applicable standards.

Parameter Required Information
Panel Type MDB / MCC / DB / Control Panel
Rated Voltage [V]
Frequency [Hz]
Rated Current [A]
Short-Circuit Rating [kA]
Incomer ACB / MCCB / Other
Busbar Copper / As specified
IP Rating [IP Rating]
Internal Separation [Required Form]
Dimensions W × H × D
Cable Entry Top / Bottom / Side
Metering As specified
Protection As approved
Control As specified
Communication As required
Applicable Standards Project requirements
Testing Routine verification / FAT
Documentation Drawings, datasheets and test records

Final Shop Drawing Approval Checklist

 Before approving a panel shop drawing, the project team should confirm that the electrical, mechanical, installation and documentation requirements have been addressed. A structured checklist makes the review faster and more consistent.

Electrical

  • Voltage confirmed
  • Frequency confirmed
  • Current rating confirmed
  • Fault level confirmed
  • Incomer confirmed
  • Outgoing breakers confirmed
  • Busbar rating confirmed
  • Protection requirements confirmed
  • Metering confirmed

Mechanical

  • Panel dimensions checked
  • Door access checked
  • Cable entry checked
  • Mounting arrangement checked
  • IP rating confirmed
  • Maintenance access checked
  • Panel weight considered

Documentation

  • GA drawing included
  • SLD included
  • Schematics included
  • Datasheets included
  • Component schedule included
  • Compliance documents included
  • Revision history updated
  • Comments addressed

Installation

  • Room layout checked
  • Cable trench checked
  • Access route checked
  • Clearance checked
  • Incoming/outgoing cable routes confirmed

Download the Panel Shop Drawing Submittal Checklist

A standard submittal checklist helps consultants, contractors and panel manufacturers verify that the required drawings and technical documents are complete before formal submission. This can reduce unnecessary review cycles and manufacturing delays.

The checklist can be used for:

  • MDB submissions
  • MCC submissions
  • Distribution boards
  • APFC panels
  • VFD panels
  • ATS/MTS panels
  • Control panels
  • Solar distribution panels

For additional technical resources, visit the Paneltech Systems Knowledge Centre.


Contact Paneltech Systems Ltd

Powering Kenya's Future with Reliable Electrical Solutions

Email: [email protected]
Phone: 0799 531765
Location: Nairobi, Kenya
Website: Paneltech Systems Ltd

Our Specialized Services

  • Low Voltage (LV) Panels & APFC Panels
  • VFD Drive Solutions & ATS / MTS Systems
  • Solar Power & EV Charging Infrastructure
  • Electrical Supplies & Engineering Consultations

For shop drawing approval, panel GA drawing preparation, technical submittals or custom LV panel requirements, contact Paneltech Systems Ltd before manufacturing begins so the electrical and physical requirements can be properly coordinated.